Risk Assessment

Funding

Project has no dedicated funding sources.

Contingency: Locations should be prioritized based on feasibility and potential for use.

Siting Problems

Private land owners may decline charging station installation.

Contingency: Possible locations should include both private and city-owned property.

Environmental Impact

Environmental impacts are unknown until locations are identified and assessed.

Contingency: If an environmental impact statement (EIS) needs to be completed, the project team may choose to prioritize a location that does not have an environmental impact.